HI District Staff Members,
Below is our new, more informative bond report format.
A few Extras to Note:
- On January 5th we will start our district-wide committees to begin planning for the equipment, technology, and furniture components of the bond. Two staff members from each site will meet with me for lunch at the Coliseum. Those members will help keep the sites informed as we move forward.
- The district is on the fastest schedule legally possible to ensure that EMS and Safe Rooms start as ASAP! It takes MONTHS to get these things in place, but we are not wasting a day to ensure that we break ground in the Spring – as promised -- (Please see: Toby Dawn the Christmas Elf)
- We had the LAWTON CAN Page to share information (it is still there, to keep us honest), but we have added the LAWTON SIP Page to store all updates and information as we move forward – it just launched, so it is not fully populated: http://www.lawtonps.org/lawton-sip-2017
District staff members have worked extremely hard to move as fast as possible. We owe it to you to deliver on this bond and to keep you informed.
Lawton Public Schools
Bond & Sales Tax Projects – Completion Status As of December 14, 2017
(The purpose of this update is to ensure that stakeholders understand the process and movement as the district utilizes bond and sales tax funds. Timelines and processes may change or adjust in some measure due to delays, unexpected problems, overruns or weather.)
Major 2017 Facilities Bond Projects
Eisenhower Middle School | Ongoing site plan meetings | Pre-Design Phase |
|
& Safe Room Plans |
| ||
|
| ||
|
| ||
SAFE ROOMS |
| ||
Elementary: |
| ||
Almor West | Ongoing site plan meetings | Design Phase |
|
Carriage Hills | Ongoing site plan meetings | Design Phase |
|
Crosby Park | Ongoing site plan meetings | Design Phase |
|
Edison | Ongoing site plan meetings | Design Phase |
|
Hugh Bish | Ongoing site plan meetings | Design Phase |
|
Sullivan Village | Ongoing site plan meetings | Design Phase |
|
Whittier | Ongoing site plan meetings | Design Phase |
|
Woodland Hills | Ongoing site plan meetings | Design Phase |
|
| |||
| |||
EQUIPMENT, TECHNOLOGY AND FURNITURE |
| ||
**Principals provided input in December regarding timelines. District-wide committee members will meet in January to discuss needs and processes. |
| ||
| |||
| |||
Current Projects |
| ||
**Below is an update of all current AIP projects not related to the 2017 Bond Program |
| ||
|
|
| |
Major 2014 Bond & Sales Tax Projects
|
|
|
|
HVAC PROJECTS |
|
|
|
MacArthur Middle School | Work started | In Progress |
|
John Adams Elementary | Pre-construction conference | Materials scheduled for delivery |
|
Lincoln Elementary | Pre-construction conference | Materials scheduled for delivery |
|
Woodland Hills Elementary | Pre-construction conference | Materials scheduled for delivery |
|
|
|
|
|
ROOF PROJECTS |
|
|
|
Lawton High School
| Auxiliary gym complete, main gym substantially complete | In Progress
|
|
Tomlinson Middle School | Work started |
In Progress |
|
|
|
|
|
John Adams Elementary | Postponed until HVAC is complete |
|
|
Carriage Hills Elementary | Substantially complete | In Progress |
|
Edison Elementary | Work started | In Progress |
|
WINDOW PROJECTS |
|
|
|
Eisenhower High School | Completion of punch list items | In Progress |
|
Lawton High School | Materials ordered | Estimated start time: End of Jan 2018 |
|
MacArthur High School | Bids accepted 12/11/17 |
|
|
Douglass Learning Center | Architect Plans Complete | Bid Dates TBD |
|
|
|
|
|
CAFETERIA RENOVATION |
|
|
|
MacArthur High School | Pre-construction conference | Scheduled to start Summer 2018 |
|
LAWTON CAN!
God Bless,
Tom Deighan
Superintendent, Lawton Public Schools