2017 SIP Update

HI District Staff Members,

Below is our new, more informative bond report format.  

A few Extras to Note:

  • On January 5th we will start our district-wide committees to begin planning for the equipment, technology, and furniture components of the bond.  Two staff members from each site will meet with me for lunch at the Coliseum.   Those members will help keep the sites informed as we move forward.
  • The district is on the fastest schedule legally possible to ensure that EMS and Safe Rooms start as ASAP!  It takes MONTHS to get these things in place, but we are not wasting a day to ensure that we break ground in the Spring – as promised -- (Please see: Toby Dawn the Christmas Elf)
  • We had the LAWTON CAN Page to share information (it is still there, to keep us honest), but we have added the LAWTON SIP Page to store all updates and information as we move forward – it just launched, so it is not fully populated:  http://www.lawtonps.org/lawton-sip-2017

District staff members have worked extremely hard to move as fast as possible.  We owe it to you to deliver on this bond and to keep you informed.

Lawton Public Schools

Bond & Sales Tax Projects  –  Completion Status As of December 14, 2017

(The purpose of this update is to ensure that stakeholders understand the process and movement as the district utilizes bond and sales tax funds.  Timelines and processes may change or adjust in some measure due to delays, unexpected problems, overruns or weather.)

 

Major 2017 Facilities Bond Projects

Eisenhower Middle School

Ongoing site plan meetings

Pre-Design Phase

 

& Safe Room Plans

 

 

 

 

 

SAFE ROOMS

 

Elementary:

 

Almor West

Ongoing site plan meetings

Design Phase

 

Carriage Hills

Ongoing site plan meetings

Design Phase

 

Crosby Park

Ongoing site plan meetings

Design Phase

 

Edison

Ongoing site plan meetings

Design Phase

 

Hugh Bish

Ongoing site plan meetings

Design Phase

 

Sullivan Village

Ongoing site plan meetings

Design Phase

 

Whittier

Ongoing site plan meetings

Design Phase

 

Woodland Hills

Ongoing site plan meetings

Design Phase

 

 

 

EQUIPMENT, TECHNOLOGY AND FURNITURE

 

**Principals provided input in December regarding timelines. District-wide committee members will meet in January to discuss needs and processes.

 

 

 

 

 

 

 

Current Projects

 

**Below is an update of all current AIP projects not related to the 2017 Bond Program

 

 

 

 

Major 2014 Bond & Sales Tax Projects

 

 

 

 

HVAC PROJECTS

 

 

 

MacArthur Middle School

Work started

In Progress

 

 

John Adams Elementary

Pre-construction conference

Materials scheduled for delivery

 

Lincoln Elementary

Pre-construction conference

Materials scheduled for delivery

 

Woodland Hills Elementary

Pre-construction conference

Materials scheduled for delivery

 

 

 

 

 

ROOF PROJECTS

 

 

 

Lawton High School

 

Auxiliary gym complete, main gym substantially complete

In Progress

 

 

 

Tomlinson Middle School

Work started

 

In Progress

 

 

 

 

 

John Adams Elementary

Postponed until HVAC is complete

 

 

Carriage Hills Elementary

Substantially complete

In Progress

 

Edison Elementary

Work started

In Progress

 

 

WINDOW PROJECTS

 

 

 

Eisenhower High School

Completion of punch list items

In Progress

 

Lawton High School

Materials ordered

Estimated start time: End of Jan 2018

 

MacArthur High School

Bids accepted 12/11/17

 

 

Douglass Learning Center

Architect Plans Complete

Bid Dates TBD

 

 

 

 

 

 

CAFETERIA RENOVATION

 

 

 

MacArthur High School

Pre-construction conference

Scheduled to start Summer 2018

 

LAWTON CAN!

God Bless,

Tom Deighan

Superintendent, Lawton Public Schools